Certification Questions

Q:

The schedule performance index (SPI) is calculated as

A) Planned Value (PV) divided by Earned Value (EV) B) Earned Value(EV) divided by Planned Value (PV)
C) Project duration divided by Earned Value divided by Planned Value (Duration/(EV/PV)) D) Earned Value (EV) minus Planned Value (PV)
 
Answer & Explanation Answer: B) Earned Value(EV) divided by Planned Value (PV)

Explanation:

Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance. 

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4610
Q:

The procurement documents to be used, the supplier management processes and the types of contracts that will be used are to be found in which document?

A) Solicitation management plan. B) Contracting management plan.
C) Organizational policies. D) Procurement management plan.
 
Answer & Explanation Answer: D) Procurement management plan.

Explanation:

Key elements in the procurement management plan are enumerated in this PMBOK section. [12.1.3.1]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3330
Q:

Which of the following is usually not considered a goal of portfolio management?

A) To manage the effective and efficient use of resources. B) To balance the portfolio among incremental and radical investments.
C) To maximize the value of the portfolio by careful examination of candidate projects and exclusion of those no meeting strategic objectives. D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.
 
Answer & Explanation Answer: D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.

Explanation:

There is not necessarily a relationship between projects in a portfolio. Answer D is actually one of the goals of PROGRAM management. PMBOK Guide [1.4]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4112
Q:

Integration is primarily concerned with

A) ensuring that the time, scope and cost baselines are consistent with an acceptable quality standard and with the customer’s expectations. B) getting people working together effectively toward common project goals through appropriate training, management and leadership.
C) effectively integrating the processes among the project management process groups that are required to accomplish project objectives with an organization’s defined procedures. D) ensuring that all the tools and techniques of the various planning processes are appropriately scaled to the complexity and risk exposure of the project.
 
Answer & Explanation Answer: C) effectively integrating the processes among the project management process groups that are required to accomplish project objectives with an organization’s defined procedures.

Explanation:

Answers A, B and D all result from effectively integrating the work of the project management process groups. PMBOK [4.0]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 2584
Q:

A statistical method for identifying which factors may influence specific variables of a product or process under development or in production is called

A) cost benefit analysis. B) sensitivity analysis.
C) cost of quality analysis. D) design of experiments.
 
Answer & Explanation Answer: D) design of experiments.

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

11 11211
Q:

The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

A) Performance management B) Scope identification
C) Risk identification D) Project team status meeting
 
Answer & Explanation Answer: C) Risk identification

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

7 11860
Q:

The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?

A) Change control system B) Process analysis
C) Benchmarking D) Configuration management system
 
Answer & Explanation Answer: B) Process analysis

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

1 7571
Q:

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

A) Additional resources using the contingency fund B) Escalation approval to use contingency funding
C) Team overtime to meet schedule D) Corrective action based on causes
 
Answer & Explanation Answer: D) Corrective action based on causes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

16 12811